Pedestrian Bridge Installation
The timetable for the new bridge is as follows:
W/C 22nd August 2022 – Tree works along Old Lane - access to the canoe club from Old Lane will remain unchanged.
W/C 5th September 2022 – Foundation and verge works – Access will remain unchanged from Old Lane to the canoe club for pedestrians, however there may be localised closures for vehicles.
W/C 19th September 2022 – Bridge installation Works – Access will not be permitted to the canoe club from Old Lane for vehicles or pedestrians.
W/C 26th September 2022 – Ramp installation works – Access will remain unchanged from Old Lane to the canoe club for pedestrians, however there may be localised closures for vehicles.